05 November 2019A5 KILSBY TO WEEDON Multi-Disciplinary Project Update Bulletin 16 – 31.10.2019

Between 8pm and 6am each night, from Monday 4th November to Friday 8th November inclusive and Monday 11th November 2019, we will be carrying out kerbing works at the B5385 Watford /  Welton junction and main drainage works in Phase 7, from B5385 Watford to A361 Kilsby roundabout. The kerbing works will require the closure of the Welton / Ashby St. Ledgers road at the junction but access will be maintained to Watford.
 
Please note that between 8pm Tuesday 5th and 6am Wednesday 6th November 2019, we are planning to carry out High Friction Surfacing using temporary 2-way traffic signal control in Phase 5, between Daventry Road (Norton) and B4036 Long Buckby.
 
Please also note that as currently, there are no works planned on the A5 between 6am Saturday 9th and 8pm Monday 11th November 2019, the road will be open to through traffic between Kilsby and Weedon.
 
Following this second weather related postponement of resurfacing works in Phase 6, from B4036 Long Buckby to B5385 Watford, we are now planning to carry out these works over two weekends later in November 2019:
 
Between 8pm Friday 15th and 6am Monday 18th November 2019 and
 
between 8pm Friday 22nd and 6am Monday 25th November 2019.
 
Please note that all our planned road works may be subject to change due to weather conditions or unforeseen circumstances. 